Ballymore National Rugby Training Centre construction update - November 2022

Wed, Dec 7, 2022, 6:00 AM
Jim Tucker
by Jim Tucker

November provided plenty of key milestones in the construction phase of the National Rugby Training Centre at Ballymore - see below for the full list:

  • Completed the removal of the existing turf from Field 3
  • Installation of window glazing to the building’s northern façade
  • Plastering (set and sand) works commenced to the internal walls and ceilings on ground floor
  • Structure install commenced to the ground floor swimming pools
  • Completed the last internal concrete pour (main entry reception stairs)
  • Installation commenced of the roof plant deck equipment
  • Commenced external cladding install to the building’s northern façade
  • ‘Angus’ The Tower Crane dismantled and removed on 17/11/2022
  • Ministerial Visit held on-site 11/11/2022 with Member of Parliament Grace Grace

The last pour for the main Entrance stairs has been poured.

Players entrance onto the field.

Vista of the McLean stand from the Southern end.

Ministerial visit to the NRTC from Grace Grace MP.

Share
Sunnybank's Junior Laloifi in action for the Australian Sevens team in 2013. Photo: Matt Roberts, Getty Images
Ballymore Beat: Junior Laloifi To Reach 100-game Milestone for Sunnybank
Finn Mackay (left) and Nick Conway (right) have been signed to deals with the Queensland Reds
Queensland Reds sign Nick Conway and Finn Mackay
Edmed, Salakaia-Loto named in Wallabies squad for Springboks Tests
‘Outside your comfort zone’: Caslick excited to take new skills back to Sevens, hopes for closer ties with Wallaroos