Ballymore National Rugby Training Centre construction update - November 2022

Wed, Dec 7, 2022, 6:00 AM
Queensland Rugby Media Unit
by Queensland Rugby Media Unit

November provided plenty of key milestones in the construction phase of the National Rugby Training Centre at Ballymore - see below for the full list:

  • Completed the removal of the existing turf from Field 3
  • Installation of window glazing to the building’s northern façade
  • Plastering (set and sand) works commenced to the internal walls and ceilings on ground floor
  • Structure install commenced to the ground floor swimming pools
  • Completed the last internal concrete pour (main entry reception stairs)
  • Installation commenced of the roof plant deck equipment
  • Commenced external cladding install to the building’s northern façade
  • ‘Angus’ The Tower Crane dismantled and removed on 17/11/2022
  • Ministerial Visit held on-site 11/11/2022 with Member of Parliament Grace Grace

The last pour for the main Entrance stairs has been poured.

Players entrance onto the field.

Vista of the McLean stand from the Southern end.

Ministerial visit to the NRTC from Grace Grace MP.

Share
Harry Wilson is confident the new look flyhalves can deal with the Test pressure. Photo: Getty Images
Wallabies skipper Wilson backing debutant, make shift flyhalf to rise to France Test
Reds halfback Sarah Dougherty in action. Photo: Chris Hyde, Getty Images
Ballymore Beat: Halfback Hero Ready for More from Reds Women in Fiji
Declan Meredith named for Wallabies debut against France
Tom Hooper signs with Queensland Reds from 2028 in return to Australian Rugby