Ballymore National Rugby Training Centre construction update - October 2022

Wed, Dec 7, 2022, 5:30 AM
Jim Tucker
by Jim Tucker

It's been another busy month at Ballymore with the National Rugby Training Centre (NRTC) taking shape. See below a list of items completed during the month of October:

  • Completed the remaining roof sheeting and box gutter install to the upper roof
  • Commenced the installation of the façade framing & back panning to all elevations
  • Completed the majority of services rough-in on ground floor with Level 1 now commencing
  • Commenced installation of the upper roof plant deck
  • Commenced framing to the eastern soffit overhanging the grandstand
  • Commenced formwork to the main entry reception stairs
  • Delivery of the mechanical AHUs and performance gym ceiling fans
  • Completed majority of internal framing to the ground floor with sheeting works commencing
  • Commenced structure works for the swimming pools
  • Commenced installation of the ground level and level 1 external window framing on all elevations
  • Commenced formwork installation to the main feature stairs located in the reception

Share
Sunnybank's Junior Laloifi in action for Brisbane City in 2016. Photo: Bradley Kanaris, Getty Images
Ballymore Beat: Junior Laloifi To Reach 100-game Milestone for Sunnybank
Finn Mackay (left) and Nick Conway (right) have been signed to deals with the Queensland Reds
Queensland Reds sign Nick Conway and Finn Mackay
Edmed, Salakaia-Loto named in Wallabies squad for Springboks Tests
‘Outside your comfort zone’: Caslick excited to take new skills back to Sevens, hopes for closer ties with Wallaroos