It's been another busy month at Ballymore with the National Rugby Training Centre (NRTC) taking shape. See below a list of items completed during the month of October:
- Completed the remaining roof sheeting and box gutter install to the upper roof
- Commenced the installation of the façade framing & back panning to all elevations
- Completed the majority of services rough-in on ground floor with Level 1 now commencing
- Commenced installation of the upper roof plant deck
- Commenced framing to the eastern soffit overhanging the grandstand
- Commenced formwork to the main entry reception stairs
- Delivery of the mechanical AHUs and performance gym ceiling fans
- Completed majority of internal framing to the ground floor with sheeting works commencing
- Commenced structure works for the swimming pools
- Commenced installation of the ground level and level 1 external window framing on all elevations
- Commenced formwork installation to the main feature stairs located in the reception